Decommissioning Insight 2020
OUTOF SERVICE
5.2 The Decommissioning Work Breakdown Structure — Ten-Year Expenditure Forecast
Figure 8: Work Breakdown Structure and Expenditure Proportion, 2020–29
OUTOF SERVICE
1 Project Management
2 Post-CoP Running Costs
3 Well Decommissioning
4 Facilities & Pipelines Permanent Isolation & Cleaning
5 Topsides Preparation
6 Topsides Removal
7 Substructure Removal
8 Topsides and Sub-structure Onshore Disposal
9 Subsea Infrastructure
10 Site Remediation
11 Post- Decommissioning Monitoring
Proportion of Overall Ten-Year Expenditure (£MM)
7% 9% 49% 3% 3% 8% 6% 2% 11% 1% <1% TOTAL
Northern North Sea & West of Shetland
£14.35 £5,950.40
£389.04 £520.75
£2,940.09
£241.40
£193.39
£703.01
£265.59
£123.96
£519.68
£39.14
Central North Sea £418.52 £672.60
£3,162.60
£95.90
£183.65
£300.47
£247.17
£147.19
£786.15
£39.49
£19.50 £6,073.25
Southern North Sea & East Irish Sea
£191.15 £176.22
£1,287.77
£87.90
£105.20
£253.84
£417.00
£94.23
£316.61
£94.23
£25.53 £3,049.69
TOTAL £998.71 £1,369.57
£7,390.46
£425.20
£482.24 £1,257.32 £929.76 £365.38 £1,622.44
£172.86
£59.38 £15,073.34