Decommissioning Insight 2018
DECOMMISSIONING INSIGHT 2018
Figure 10: Historical Variation in Removal Costs per Tonne in Central and Northern North Sea and West of Shetland
16,000
Average Forecast Topside Removal Cost per Tonne Average Forecast Substructure Removal Cost per Tonne
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Estimated Cost per Tonne (£ - 2017 Money)
0
2014 2015 2016 2017 2018
2014 2015 2016 2017 2018
Topside
Substructure
Source: Oil & Gas UK, OGA
Removal Cost Per Tonne 2016 Survey
2017 Survey
2018 Survey
Topsides
£3,710 £4,436
£2,757 £4,722
£2,404 £3,953
Substructure
Figure 11: Historical Variation in Removal Costs per Tonne in Southern North Sea and Irish Sea
18,000
16,000
14,000
12,000
10,000
8,000
6,000
4,000
2,000
Estimated Cost per Tonne (£ - 2017 Money)
0
2014
2015
2016
2017
2018
Topside and Substructure
Source: Oil & Gas UK, OGA
Removal Cost Per Tonne 2016 Survey Topsides & Substructure £3,946
2017 Survey
2018 Survey
£3,601 £3,690 Note: topsides and substructure included in the same cost as the smaller assets in the SNS are usually removed in one campaign, making it difficult to portion costs effectively.
26