4.1 Expenditure Breakdown
Figure 5 shows the spread of costs over a decommissioning project. The forecast proportions of decommissioning expenditures over the next ten years bear similarities to previous Decommissioning Insight reports.
Figure 5: WBS Expenditure by Activity, 2018 to 2027
Topsides & Substructure Onshore Recycling ● Onshore waste handling ● Deconstruction ● Decontamination
Subsea Infrastructure & Pipelines ● Removal of Pipelines ● Removal of Mattresses ● Removal of Subsea structures
Site Remediation and Post-decommissioning Monitoring ● Debris Clearance ●Monitoring Requirements
Removals ● Removal activities for the topsides ● Removal activities for the substructure
4
2%
12%
Facilities & Pipeline De-energising and Topside Preparation ● Engineering down and cleaning topsides and pipelines ● Preparation of platform for unattended mode
2%
13%
5%
Well Decommissioning ● Spread rate and services
associated with phase 1, phase 2 and phase 3 decommissioning of wells Operator Costs ● Project management services throughout Preparation of decommissioning programme ● (Post CoP OPEX) Operational expenditure after occurrence of Cessation of Production
49%
17%
Source: Oil & Gas UK, OGA